Beveridge SW Merrifield Nth (BSWMN) RORB Models.

Three options:
Predevelopment - Assuming rural land use (FI = 0.05).
Postdevelopment Option 1 (Main Report)- Maintain original 5 waterways/drainage lines with 5 crossings of the OMRR. Assume draft PSP land use.
Postdevelopment Option 2 (Addendum Report) - Diversion of Kalkallo Creek to western constructed waterway within BSW PSP, with 4 crossings of the OMRR. Assume draft PSP land use.

Events:
For predevelopment, 1% AEP SSP1 was run. 
For postdevelopment Option 1 and Option 2, 1% AEP SSP1 was run and will eventually be used for input to postdevelopment TUFLOW model. 1% AEP SSP3 and 63.2% AEP SSP3 were run for constructed waterway sizing.